🌊 JRC 항해통신 도면 자동화 시스템

25
전체 장비
5
활성 프로젝트
62%
평균 Progress

🔄 Complete Process Progress (14Stage)

📋 Stage 1-3: Order~Review Request
100%
✓ Order Receipt → Registration → Review Request Complete
🔍 Stage 4-5: JRC Review 및 전달
75%
진행 중: 9개 프로젝트 Review 중, 3개 Approval됨
⚓ Stage 6: Shipyard Comments
45%
병목 구간: 6개 프로젝트 Comments Collection 중
🔄 Stage 7-8: Modification 및 Order Issue
33%
3개 프로젝트 INSTALLATION Order Issue 대기
🏗️ Stage 9-11: Installation 도면
0%
Scheduled: 3월 초 Start
📦 Stage 12-14: Final 도면
0%
Scheduled: 4월 초 Start

📊 Project Progress Status

Project Name Current Stage Progress Status State
PRJ-2025-001 (VDR) Stage 5
✓ Approval 도면 Shipyard 전달 Complete In Progress
PRJ-2025-002 (RADAR) Stage 6
Shipyard Comments Collection 중 (3/5 Complete) Review
PRJ-2025-003 (ECDIS) Stage 6
⚠️ Comments 상충 (JRC vs Shipyard) Delayed
PRJ-2025-004 (GPS) Stage 4
JRC Review 중 (Expected: 1월 29일 Complete) In Progress
PRJ-2025-005 (AIS) Stage 3
Drawing Creation 중 (Expected: 1월 28일 Complete) In Progress
PRJ-2025-006 (VHF) Stage 3
Drawing Creation 중 (Expected: 1월 31일 Complete) In Progress

📈 Process Stage Details

📋 Stage 1-3: ORDER~Review Request
Complete 프로젝트:
6개 ✓ Complete
일정:
Scheduled대로 진행
🔍 Stage 4-5: JRC Review 및 전달
Status:
Review 중: 9개 | Approval: 3개
병목:
ECDIS 반려 (이견 조율 중)
⚓ Stage 6: Shipyard Comments
Collection 중:
6개 프로젝트 | 24개 Comments
⚠️ 병목 구간
Shipyard 일정 Delayed
🔄 Stage 7-8: Modification 및 Order Issue
대기 프로젝트:
3개 (PRJ-04, 05, 06)
Expected Start:
2월 초
🏗️ Stage 9-11: Installation 도면
Scheduled 프로젝트:
6개
Start Scheduled:
2025년 3월 초
📦 Stage 12-14: Final 도면
Scheduled 프로젝트:
6개
Start Scheduled:
2025년 4월 초

🔔 Alerts 주요 알림 & 병목 구간 Bottlenecks

🚨 병목 구간: Shipyard Comments Collection Delayed
영향 받는 프로젝트: PRJ-2025-002 (RADAR), PRJ-2025-003 (ECDIS), PRJ-2025-004 (GPS)
현황: 6개 프로젝트 중 24개 Comments Collection 중
원인: Shipyard 일정 Delayed (Expected Complete 2월 초)
조치: Shipyard와 Emergency 협의 중, 우선순위 재조정
⚠️ Comments 상충: PRJ-2025-003 (ECDIS)
문제: JRC의견 vs Shipyard의견 충돌 (설치 방식 차이)
영향: Stage 6 진행 Delayed, Installation Order Issue 미루어짐
조치: AI 자동 분석 중, JRC-Shipyard-KJE 3자 협의 Scheduled
Expected 해결: 1월 31일
ℹ️ 정상 진행 프로젝트
✓ PRJ-2025-001 (VDR): Stage 5 Complete ✓ Shipyard 전달 Complete
✓ PRJ-2025-005 (AIS): Drawing Creation 중 (Expected 1월 28일 JRC Review)
✓ PRJ-2025-006 (VHF): Drawing Creation 중 (Expected 1월 31일 JRC Review)
📅 주요 일정
1월 28일: PRJ-05 (AIS) JRC Review Start
1월 31일: PRJ-06 (VHF) JRC Review Start / ECDIS Comments 충돌 해결 Scheduled
2월 초: Shipyard Comments Collection Complete / INSTALLATION Order Issue
3월 초: INSTALLATION Drawing Creation Start

📊 Process Efficiency Analysis

⏱️ Average Processing Time
12.3일
각 Stage별 평균 소요 일정
✓ Completion Rate
33.3%
전체 14Stage 중 4.7Stage Complete
⏳ 병목 Delayed
3.2일
Expected 대비 평균 Delayed일수
🔴 Issues
2건
Shipyard 일정 Delayed, Comments 충돌

📦 프로젝트 Information

Project Name
PRJ-2025-001
주문번호 (주문번호)
PO-2025-0123
Shipyard
HHIC
선박명
선박명
선박 유형
-
선박 크기
-
선박국적 (선박국적)
-
선급 1
-
선급 2
-
부호
-
BAM 적용
-
RMS 적용
-
시리즈 선박
-
인도 예정일
-

📋 📋 도면 관리 레지스터

No 프로젝트 장비 장비명 도면번호 PO번호 현재 State Progress 담당자 Approval일
1 PRJ-2025-001 RAN RADAR X-Band JRC-RAN-01-AP PO-2025-0123 ✓ Complete 100% Lee Y.H. 2025-02-10
2 PRJ-2025-001 RAN RADAR S-Band JRC-RAN-02-AP PO-2025-0123 ⚙️ 설치 진행 75% Lee Y.H. -
3 PRJ-2025-001 ECD ECDIS Main JRC-ECD-01-AP PO-2025-0123 ⚙️ 설치 진행 70% Kim M.J. -
4 PRJ-2025-001 GPS DGPS JRC-GPS-01-AP PO-2025-0123 🔍 Review 중 50% Kim M.J. -
5 PRJ-2025-001 SPL SPEED LOG JRC-SPL-01-AP PO-2025-0123 ⏳ Approval 진행 25% Park S.Y. -

🔄 Drawing Creation 프로세스 플로우 (14 Stage)

1️⃣
Approval Drawing ORDER 수신
JRC-KJE
JRC로from Approval Drawing Order Receipt
2️⃣
ORDER Registration
KJE에서 Order Registration
Drawing Creation 준비
3️⃣
Drawing Creation 및 Review Request
Drawing Creation 후
JRC 전송 및 Review Request
4️⃣
JRC Review 및 Modification (Iterative)
JRC Review 후
Non-conformance → KJE Modification Request
↔ Iterative → Final Approval
5️⃣
Final Approval Drawing 전달
KJE → Shipyard
PDF + Hard Copy 3부
6️⃣
Shipyard COMMENTS (Iterative)
Shipyard 추가 Comments
↔ Iterative
APPROVED COMMENTS → KJE
7️⃣
APPROVED COMMENTS 반영
KJE가 Comments 반영
JRC에 Final Approval 요청
8️⃣
JRC Review 및 Order Issue
JRC Review 후
변경사항 반영 요청
INSTALLATION 도면 Order Issue
9️⃣
INSTALLATION 도면 작성
KJE INSTALLATION 도면 작성
JRC에 Final Approval 요청
🔟
JRC Final Approval
JRC로from
INSTALLATION 도면
Final Approval
1️⃣1️⃣
Shipyard에 Drawing Delivery
KJE → Shipyard
PDF + Hard Copy 3부
1️⃣2️⃣
Ship Construction
Shipyard 최종
INSTALLATION 기반
Ship Construction
1️⃣3️⃣
FINAL DRAWING Order 요청
Shipyard Owner Delivery 전
KJE → JRC
FINAL 도면 Order 요청
1️⃣4️⃣
FINAL DRAWING Creation 및 납부
JRC Order Receipt
Final Drawing Creation
Shipyard에 납부

📋 프로세스 요약

Approval Drawing Process
• Stage 1-5: Order Receipt → Registration → Creation → JRC Review(Iterative) → Approval
• Stage 6: Shipyard Comments Collection 및 반영
Review 및 Modification Stage
• Stage 4: JRC Review → Non-conformance → KJE Modification(Iterative)
• Stage 6: Shipyard Comments → Iterative Modification
• Stage 8: JRC 재Review
INSTALLATION Drawing Process
• Stage 8-11: Order Issue → 도면 작성 → JRC Approval → Shipyard 전달
• Stage 14: FINAL Drawing Creation 및 납부

👥 주요 참여자 및 역할

🏢 JRC (검사기관)
  • Order Issue
  • 도면 Review 및 Approval
  • Non-conformance 사항 지적
🏭 KJE (Drawing Creation사)
  • Order Registration
  • Drawing Creation
  • Modification사항 반영
⚓ Shipyard
  • 도면 검수
  • Comments 제시
  • Ship Construction

📦 프로젝트 Information

Project Name
PRJ-2025-001
주문번호 (주문번호)
PO-2025-0123
Shipyard
HHIC
선박명
선박명
선박 유형
-
선박 크기
-
선박국적 (선박국적)
-
선급 1
-
선급 2
-
부호
-
BAM 적용
-
RMS 적용
-
시리즈 선박
-
인도 예정일
-

⚙️ 주요 장비 현황

  • RADAR X-Band
    RAN-01 (JMA-9100)
    📦 JMR-9282-S ✓ Complete
    100%
  • ECDIS Main Display
    ECD-01 (JAN-9201)
    📦 JAN-9201 ⚙️ 설치 진행
    70%
  • GPS (DGPS)
    GPS-01
    📦 JLR-7800 🔍 Review 중
    50%
  • VHF Communication
    VHF-01
    📦 JHS-770S ⏳ 대기
    15%
  • NAVTEX Receiver
    NAV-01
    📦 NCR-333 ⏳ 대기
    5%

📊 장비별 진행 통계

총 장비 수
25개
평균 모델 수/장비
10개
평균 Components/모델
20개
총 도면 수
250개

🎯 완성 예측

Shipyard 최종 Review Complete
2025년 3월 15일
전체 프로세스 Complete
2025년 3월 20일

📦 프로젝트 Information

Project Name
PRJ-2025-001
주문번호 (주문번호)
PO-2025-0123
Shipyard
HHIC
선박명
선박명
선박 유형
-
선박 크기
-
선박국적 (선박국적)
-
선급 1
-
선급 2
-
부호
-
BAM 적용
-
RMS 적용
-
시리즈 선박
-
인도 예정일
-

🔧 표준 Components 템플릿

📦 독립 장비 (Standalone Equipment)

장비 Model 연결 타입 주요 Components OPTIONS 선택
EPIRB JQE-103 단독 Beacon, Antenna, Battery GNSS Module, Backup Battery
SART TRONSART20 단독 Beacon, Antenna, Power Supply Enhanced Range Kit

🔗 연동 장비 (Integrated Equipment)

장비 Model 연결 타입 주요 Components OPTIONS 선택
RADAR JMR-9282-S 외부 Antenna, Display, Processor, Power Supply X-Band/S-Band Selector, 고급 신호처리
ECDIS JAN-9201 내부 Display Unit, Processor, Storage, Interface Module 백업 Display, 추가 Storage, 24'' Monitor Upgrade
GPS JLR-7800 외부 Antenna, Receiver Module, Interface Card DGPS Module, RTK Support
SPEED LOG JLN-205MK2 외부 Transducer, Interface Module, Display Dual Transducer Setup
ECHO SOUNDER JFE-680-25 외부 Transducer, Display Unit, Power Supply 고주파 Transducer, 기록 기능
WEATHER FAX JAX-9B 내부 Receiver Module, Printer/Display Interface 프린터 옵션, 저장 매체
MF/HF JSS-2250 외부 Transceiver, Antenna, Interface Module 고출력 증폭기, SSB 모듈
VHF JHS-770S 내부 Transceiver, Antenna, Control Panel DSC Module, 고출력 모드
INMARSAT-C JUE-87 외부 Transceiver, Antenna, Control Unit 확장 메시지 저장소
VDR JCY-1900 내부 Recording Module, Interface Card, Storage 확장 저장소, 네트워크 백업
AIS JHS-183 외부 Transceiver, Antenna, Interface Module 이중 채널 지원
NAVTEX NCR-333 내부 Receiver, Display, Interface 다중 언어 지원